Case Study

Project name: Eldosol / Radiant Solar PV Project

Service provided: Project logistics / Project support

Industry sector: Power and Energy

Duration: 4 weeks

Cargo: 2 x 220/33kV 45 MVA transformers each 68.5 Ton

Logistics: Port handling, mafi stripping, customs clearance under temporary bond, entry perfection, loading / lashing on 8-line / 16-axles hydraulic modular trailers, permits & escorts and transport to site in Eldoret

Support: Positioning transformers on plinths via jacking / skidding method. Cold commissioning of transformers, Leasing double cab to overseas supplier’s installation team.

Project Logistics

Background image for general logistics section

General Logistics

EA Transshipment Services

Project Support Services

Oil & Gas

Mining

Infrastructure & Construction

Renewable Energy

Power & Energy