Case Study
Project name: Eldosol / Radiant Solar PV Project
Service provided: Project logistics / Project support
Industry sector: Power and Energy
Duration: 4 weeks
Cargo: 2 x 220/33kV 45 MVA transformers each 68.5 Ton
Logistics: Port handling, mafi stripping, customs clearance under temporary bond, entry perfection, loading / lashing on 8-line / 16-axles hydraulic modular trailers, permits & escorts and transport to site in Eldoret
Support: Positioning transformers on plinths via jacking / skidding method. Cold commissioning of transformers, Leasing double cab to overseas supplier’s installation team.